2.27.09 - Second to Last Progress Blog

  View this article>>
February 2, 2009
 

2.2.09 Progress Update - Acqua Liana now complete - 10 days to Grand Unveiling

  View this article>>
January 5, 2009
 

1.5.09 Progress Update - Only one more update until the Grand Unveiling!

  View this article>>
December 2, 2008
 

12.2.08 Progress Update - The house is energized with permanent power! 72 days until Acqua Liana's Grand Unveiling

  View this article>>
November 10, 2008
 

11.10.08 Progress Update - The waterwalls are cascading, 94 days until our Grand Unveiling.

  View this article>>
October 1, 2008
 

10.1.08 Progress Update - a very productive two weeks, 4 months to completion

  View this article>>
September 19, 2008
 

9.19.08 Progress Update - less than 5 months to completion

  View this article>>
August 15, 2008
 

8.15.08 Progress Update - from house to home - 14 major milestones achieved this month

  View this article>>
July 15, 2008
 

7.15.08 Progress Update - 6 months to completion...

  View this article>>
June 5, 2008
 

6.5.08 Progress Update - Most productive month yet!

  View this article>>
May 6, 2008
 

5.6.08 Progress Update - Drywall installation 50% complete

  View this article>>
April 30, 2008
 

4.30.08 Progress Update - A significant milestone: Drywall installation has commenced!

  View this article>>
April 1, 2008
 

4.1.08 Progress Update - 24' floor-to-ceiling oceanfront water wall installation has begun

  View this article>>
March 6, 2008
 

3.6.08 Progress Update - Pools, roof and solar move further along

  View this article>>
February 14, 2008
 

2.14.08 Progress Update - Installation of all doors, windows and oversized plate glass is complete (with the exception of the front door)

  View this article>>
January 21, 2008
 

1.21.08 Progress Update - Interior rough plumbing has commenced

  View this article>>
January 3, 2008
 

1.3.08 Progress Update - Happy New Year. Window installation has begun.

  View this article>>
December 27, 2007
 

12.27.07 Progress Update - Drywall framing has commenced

  View this article>>
December 12, 2007
 

12.12.07 Progress Update - Get ready to swim & look out through the windows

  View this article>>
December 4, 2007
 

12.4.07 Progress Update - Acqua Liana now "3-Dimensional"

  View this article>>
November 26, 2007
 

11.26.07 Progress Update - Concrete flooring and roof trusses

  View this article>>